1, Before the construction of the drilling rig, the following aspects of startup maintenance work must be carried out:
1. Check whether the oil level in each fuel tank is sufficient and whether the oil quality is normal;
2. Check whether the oil level of each reducer gear is sufficient and whether the oil quality is normal;
3. Check for oil leakage faults;
4. Check whether the main and auxiliary steel wire ropes have broken wires and whether their connections are safe, reliable, and intact, and whether the force of the rope press is sufficient;
5. Check if the lifting device rotates flexibly and if the internal grease is contaminated;
6. Inspect the steel structure for cracks, rust, desoldering, and other damages, and repair them;
7. Tighten loose rubber hoses and bolts;
8. Inspect and repair drill pipes in accordance with the requirements of the Simple Use and Maintenance Manual for Rotary Drilling rigs and Supporting Drill Pipes;
9. Lubrication
1) Add lubricating grease to each sports pair according to the lubrication label requirements, and the Carter engine part is lubricated according to the Carter lubrication requirements. For example, in areas with large turning surfaces such as the upper turning support, sufficient grease must be added to the entire turning surface, and every rotation must be at a certain angle;
2) Lubricating the main and auxiliary steel wire ropes, with each strand filled with butter;
3) Apply butter to all three sides of the mast track;
2, During drilling rig construction, the following daily maintenance work must be carried out on the drilling rig at all times:
1. Before each shift, the drill pipe lifting device (wire rope connector) should be lubricated with butter;
Attention: When injecting oil into the grease nozzle on one end of the elevator, be sure to unscrew the grease nozzle on the other end. This is beneficial for squeezing out the butter that was previously poured. On the contrary, it may crush the oil seal inside the elevator, making it easy for dirty water containing fine sand and mud to enter, which will wear the bearings and reduce the sensitivity of the elevator.
2. Before each shift, grease should be added to the bearings of the drill pipe follow-up guide frame (drill pipe upper bracket);
3. Regularly check if the steel wire rope is intact;
4. Regularly inspect the damage of oil pipes and sealing rings, and prepare spare parts to meet urgent needs;
5. Always pay attention to the aging of circuit relays and prepare spare parts as soon as possible;
6. Check if the bearing of the drill pipe lifter (wire rope connector) rotates flexibly. If it is damaged, it should be replaced immediately;
7. Regularly check whether the bolts and pins are worn or broken, and replace them immediately if there is any damage.